Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

  • 5th May: ` wn-2020-xma - wn-2022-lenovo` will be set to drain.

  • 9th May :

  • 10-11th May: Let the updated workers run for a few days.

  • 12th May: `wn-2017-dell (all 2017’s) - wn-2019-dell` will be set to drain.

  • 15th May: Repeat above process for second half of workers.

  • 16th May: Merge all required sandboxes into prod and manage farm back into `prod_batch` in A(9:30 am): Draining of first half of worker-nodes

  • 11th May (9:30 am): Update drained worker-nodes

  • Bring back online updated tranches

  • 11th May (16:00): Drain remaining half of worker-nodes

  • 12th May (14:00): Update drained worker-nodes

  • 12th may Bring back online updated tranches

  • Health check entire farm

Plots and associated info

...